Maine Airport Repairs Could Close Airport to Some
Repairs to the main runway at the Augusta State Airport could mean there will be no commercial flights to or from the Maine capital for up to two months.
Construction is set to begin on a $7.5 million project to renovate the runway and other improvements.
The current plan is to close the 5,100-foot main runway for 45 to 60 days. The project is set to begin May 13.
During that period no planes that need more than 2,700-feet of runway space will be allowed to use the airport. That will include commercial Cape Air flights.
Airport Manager John Guimond tells the Kennebec Journal the runway is being reconstructed for the first time in 40 to 50 years.
Guimond says it’s the perfect time for the improvements.
Copyright 2026 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.
Popular Today
- Report: Property Claims Face Delays, Are Growing More Complex
- Warren, Hawley Press Insurers Over Closed, Unpaid Claims
- First Atlantic Hurricane of 2026 to Threaten US Gulf Coast
- Agentic Intelligence for Claims Dominates New Tech Launches
Popular This Month
- Credit Acceptance Reaches $710M Predatory Auto Lending Settlement With Most States
- Are We Training Claims Adjusters or Claims Processors?
- Severe Convective Storms: Risk, Field Reality and the Path to Resilience
- The Great Hemp Reset: How the Federal Ban on Intoxicating Hemp Products Will Reshape Risk and Coverage